Planning a pre-engineered metal building in North Idaho

What to settle before you order a PEMB: loads, foundations, lead times, insulation, doors and permits.

Pre-engineered metal buildings are an efficient way to get a large, clear-span building. They also have a specific order of operations, and most problems come from doing steps out of order.

1. Confirm the design loads for your exact site

Snow loads in North Idaho vary widely with elevation and location, and they drive the cost of the frame. Get the design snow, wind and seismic criteria from the building department for your site before you request quotes, and make sure every supplier quotes to the same criteria. Also plan for drifting where roofs step or abut taller structures, and for snow sliding off the roof at doors and walkways.

2. Let the building drive the foundation

The foundation is designed from the building supplier's column reactions and anchor bolt layout. That information usually comes after the building is ordered, so the foundation design and pour must be scheduled around it. Anchor bolts must be set accurately; errors here are expensive to fix.

3. Plan for lead times

Building packages are fabricated to order. Delivery can take several months depending on the supplier and season, so confirm current lead times and order early. Site work and foundations can often proceed while the building is fabricated.

4. Decide on insulation and condensation control

A cold-climate metal building needs a deliberate insulation and vapor control strategy. Heated buildings in particular need attention at the roof and walls to avoid condensation and dripping.

5. Get doors and openings right in the order

Overhead doors, framed openings, windows and any future expansion endwall should be in the building order. Adding large openings later can require structural changes.

6. Design the slab for the use

Forklifts, racking, vehicle lifts and heavy equipment each affect slab thickness, reinforcing and joint layout. Tell your builder how the floor will be used before the slab is designed.

7. Permits and site

Expect stamped building drawings, foundation design, and site plans for permit. Rural sites may also need driveway, septic, well and fire access approvals. Start these early.


General information only. Codes, loads and requirements vary by site and jurisdiction. Confirm specifics with your design professionals and the authority having jurisdiction.